Canberra Gas Mains - Delivering gas to Australia's national capital

Length30 kmDiameter250 mm
 
Manhours50,607Lost-time injuries0
 

Engineering, procurement and construction of two stages of the pipeline connecting Canberra to the Eastern Gas Pipeline, increasing the city's gas supply and providing an alternative supply to the region.
Though fairly short, the pipeline was challenging, with HDD and trenching through national parks and many small properties. So landholder liaison, cultural heritage and environmental management were important priorities.